Annual report pursuant to Section 13 and 15(d)

Commitments And Contingencies (Tax Abatement Agreements) (Narrative) (Details)

v3.10.0.1
Commitments And Contingencies (Tax Abatement Agreements) (Narrative) (Details) - USD ($)
$ in Millions
12 Months Ended 16 Months Ended 60 Months Ended
Dec. 31, 2018
Dec. 31, 2017
Dec. 31, 2016
Apr. 30, 2017
Apr. 30, 2022
Commitments And Contingencies [Line Items]          
Percentage of PILOT on gross revenues 10.00%        
Harborside Plaza 4-A [Member]          
Commitments And Contingencies [Line Items]          
Project period 20 years        
Percentage of PILOT on project costs 2.00%        
Total project costs $ 49.5        
Payments in lieu of property taxes (PILOT) $ 1.1 $ 1.1 $ 1.1    
Harborside Plaza 5 [Member]          
Commitments And Contingencies [Line Items]          
Project period 20 years        
Percentage of PILOT on project costs 2.00%        
Total project costs $ 170.9        
Payments in lieu of property taxes (PILOT) $ 4.4 3.9 3.9    
Port Imperial South 4/5 Garage [Member]          
Commitments And Contingencies [Line Items]          
Project period 5 years        
Port Imperial South 4/5 Garage [Member] | Tax Year 1 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 0.00%        
Port Imperial South 4/5 Garage [Member] | Tax Year 2 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 80.00%        
Port Imperial South 4/5 Garage [Member] | Tax Year 3 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 80.00%        
Port Imperial South 4/5 Garage [Member] | Tax Year 4 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 80.00%        
Port Imperial South 4/5 Garage [Member] | Tax Year 5 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 80.00%        
Port Imperial South 1/3 Garage [Member]          
Commitments And Contingencies [Line Items]          
Project period 5 years        
Percentage of taxes paid based on the land value 100.00%        
Port Imperial South 1/3 Garage [Member] | Tax Year 1 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 0.00%        
Port Imperial South 1/3 Garage [Member] | Tax Year 2 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 95.00%        
Port Imperial South 1/3 Garage [Member] | Tax Year 3 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 95.00%        
Port Imperial South 1/3 Garage [Member] | Tax Year 4 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 95.00%        
Port Imperial South 1/3 Garage [Member] | Tax Year 5 [Member]          
Commitments And Contingencies [Line Items]          
Annual percentage of cost for phase in 95.00%        
Port Imperial Hotel Development [Member]          
Commitments And Contingencies [Line Items]          
Project period 15 years        
Percentage of PILOT on project costs 2.00%        
Port Imperial South 11 Development [Member]          
Commitments And Contingencies [Line Items]          
Project period 15 years        
Percentage of PILOT on gross revenues 10.00%        
111 River Realty [Member]          
Commitments And Contingencies [Line Items]          
Payments in lieu of property taxes (PILOT) $ 1.4 1.3 $ 0.6    
Annual Payments in lieu of property taxes (PILOT)       $ 1.2  
111 River Realty [Member] | Scenario, Forecast [Member]          
Commitments And Contingencies [Line Items]          
Annual Payments in lieu of property taxes (PILOT)         $ 1.4
Monaco [Member]          
Commitments And Contingencies [Line Items]          
Project period 10 years        
Payments in lieu of property taxes (PILOT) $ 2.4 $ 1.6      
Marbella Tower Urban Renewal Associates LLC [Member]          
Commitments And Contingencies [Line Items]          
Percentage of PILOT on project costs 15.00%        
Payments in lieu of property taxes (PILOT) $ 0.9        
Marbella II [Member]          
Commitments And Contingencies [Line Items]          
Project period 10 years        
Marbella II [Member] | Years 1-4 [Member]          
Commitments And Contingencies [Line Items]          
Percentage of PILOT on gross revenues 10.00%        
Marbella II [Member] | Years 5-8 [Member]          
Commitments And Contingencies [Line Items]          
Percentage of PILOT on gross revenues 12.00%        
Marbella II [Member] | Years 9-10 [Member]          
Commitments And Contingencies [Line Items]          
Percentage of PILOT on gross revenues 14.00%        
Port Imperial South Parcel 8/9 [Member]          
Commitments And Contingencies [Line Items]          
Project period 25 years        
Port Imperial South Parcel 8/9 [Member] | Years 1-10 [Member]          
Commitments And Contingencies [Line Items]          
Percentage of PILOT on gross revenues 11.00%        
Port Imperial South Parcel 8/9 [Member] | Years 11-18 [Member]          
Commitments And Contingencies [Line Items]          
Percentage of PILOT on gross revenues 12.50%        
Port Imperial South Parcel 8/9 [Member] | Years 19-25 [Member]          
Commitments And Contingencies [Line Items]          
Percentage of PILOT on gross revenues 14.00%