13. COMMITMENTS AND CONTINGENCIES
TAX ABATEMENT AGREEMENTS Pursuant to agreements with the City of Jersey City, New Jersey, the Company is required to make payments in lieu of property taxes (“PILOT”) on certain of its properties located in Jersey City, as follows:
The Harborside Plaza 4-A agreement, as amended, which commenced in 2002, is for a term of 20 years. The PILOT is equal to two percent of Total Project Costs, as defined. Total Project Costs are $49.5 million. The PILOT totaled $247,000 and $247,000 for the three months ended September 30, 2012 and 2011, respectively, and $742,000 and $742,000 for the nine months ended September 30, 2012 and 2011, respectively.
The Harborside Plaza 5 agreement, as amended, which commenced in 2002, is for a term of 20 years. The PILOT is equal to two percent of Total Project Costs, as defined. Total Project Costs are $170.9 million. The PILOT totaled $854,000 and $854,000 for the three months ended September 30, 2012 and 2011, respectively, and $2.6 million and $2.6 million for the nine months ended September 30, 2012 and 2011, respectively.
At the conclusion of the above-referenced PILOT agreements, it is expected that the properties will be assessed by the municipality and be subject to real estate taxes at the then prevailing rates.
LITIGATION The Company is a defendant in litigation arising in the normal course of its business activities. Management does not believe that the ultimate resolution of these matters will have a materially adverse effect upon the Company’s financial condition taken as whole.
GROUND LEASE AGREEMENTS Future minimum rental payments under the terms of all non-cancelable ground leases under which the Company is the lessee, as of September 30, 2012, are as follows: (dollars in thousands)
Ground lease expense incurred by the Company during the three months ended September 30, 2012 and 2011 amounted to $102,000 and $102,000, respectively, and $305,000 and $305,000 for the nine months ended September 30, 2012 and 2011, respectively.
OTHER The Company may not dispose of or distribute certain of its properties, currently comprised of seven properties with an aggregate net book value of approximately $129.6 million, which were originally contributed by certain unrelated common unitholders, without the express written consent of such common unitholders, as applicable, except in a manner which does not result in recognition of any built-in-gain (which may result in an income tax liability) or which reimburses the appropriate specific common unitholders for the tax consequences of the recognition of such built-in-gains (collectively, the “Property Lock-Ups”). The aforementioned restrictions do not apply in the event that the Company sells all of its properties or in connection with a sale transaction which the Company’s Board of Directors determines is reasonably necessary to satisfy a material monetary default on any unsecured debt, judgment or liability of the Company or to cure any material monetary default on any mortgage secured by a property. The Property Lock-Ups expire periodically through 2016. Upon the expiration of the Property Lock-Ups, the Company is generally required to use commercially reasonable efforts to prevent any sale, transfer or other disposition of the subject properties from resulting in the recognition of built-in gain to the specific common unitholders, which include members of the Mack Group (which includes William L. Mack, Chairman of the Company’s Board of Directors; David S. Mack, director; Earle I. Mack, a former director; and Mitchell E. Hersh, president, chief executive officer and director), the Robert Martin Group (which includes Robert F. Weinberg, a former director; and Timothy M. Jones, former president), the Cali Group (which includes John R. Cali, a former director, and John J. Cali, a former director). 127 of the Company’s properties, with an aggregate net book value of $1.7 billion, have lapsed restrictions and are subject to these conditions.
In August 2011, the Company commenced construction of a 203,000 square foot office building which is pre-leased for 15 years and three months, subject to two extension options of between five and 10 years each, to Wyndham Worldwide. Wyndham currently leases space in neighboring buildings in the Mack-Cali Business Campus in Parsippany, New Jersey. The new building is expected to be delivered to the tenant in the first quarter of 2013 at a total estimated cost, including leasing costs, of approximately $53.5 million (of which the Company has incurred $30.7 million through September 30, 2012, including $13.0 million of land costs).
In December 2011, the Company entered into a development agreement (the “Development Agreement”) with Ironstate Development LLC (“Ironstate”) for the development of residential towers with associated parking and ancillary retail space on land owned by the Company at its Harborside Financial Center complex in Jersey City, New Jersey (the “Harborside Residential Project”). The first phase of the project is expected to consist of a parking pedestal to support a high-rise tower of approximately 766 apartment units and estimated to cost approximately $243 million. The parties anticipate the first phase will be ready for occupancy by approximately the second quarter of 2015.
Pursuant to the Development Agreement, the Company and Ironstate shall co-develop the Harborside Residential Project with Ironstate responsible for obtaining all required development permits and approvals. Major decisions with respect to the Harborside Residential Project will require the consent of the Company and Ironstate. The Company and Ironstate will have 85 and 15 percent interests, respectively, in the Harborside Residential Project. The Company will receive capital credit of $30 per approved developable square foot for its land.
The Development Agreement is subject to obtaining required approvals and development financing as well as numerous customary undertakings, covenants, obligations and conditions. The Company has the right to reasonably determine that any phase of the Harborside Residential Project is not economically viable and may elect not to proceed, subject to certain conditions, with no further obligations to Ironstate other than reimbursement to Ironstate of all or a portion of the costs incurred by it to obtain any required approvals.
In July 2012, the Company entered into a ground lease with Wegmans Food Markets, Inc. (“Wegmans”) at its undeveloped site located at Sylvan Way and Ridgedale Avenue in Hanover Township, New Jersey. Subject to receiving all necessary governmental approvals, Wegmans intends to construct a store of approximately 140,000 square feet on a finished pad to be delivered by the Company in the first quarter of 2014. The Company expects to incur costs of approximately $12.1 million for the construction of the finished pad (of which the Company has incurred $0.5 million through September 30, 2012).
|