Quarterly report pursuant to Section 13 or 15(d)

Commitments And Contingencies (Tax Abatement Agreements) (Narrative) (Details)

v3.10.0.1
Commitments And Contingencies (Tax Abatement Agreements) (Narrative) (Details) - USD ($)
3 Months Ended 9 Months Ended 16 Months Ended 60 Months Ended
Sep. 30, 2018
Sep. 30, 2017
Sep. 30, 2018
Sep. 30, 2017
Apr. 30, 2017
Apr. 30, 2022
Harborside Plaza 4-A [Member]            
Commitments And Contingencies [Line Items]            
Project period     20 years      
Percentage of PILOT on project costs     2.00%      
Total project costs     $ 49,500,000      
Payments in lieu of property taxes (PILOT) $ 270,000 $ 345,000 $ 810,000 $ 1,000,000    
Harborside Plaza 5 [Member]            
Commitments And Contingencies [Line Items]            
Project period     20 years      
Percentage of PILOT on project costs     2.00%      
Total project costs     $ 170,900,000      
Payments in lieu of property taxes (PILOT) 1,100,000 1,200,000 $ 3,300,000 3,800,000    
Port Imperial South 4/5 Garage [Member]            
Commitments And Contingencies [Line Items]            
Project period     5 years      
Port Imperial South 4/5 Garage [Member] | Tax Year 1 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     0.00%      
Port Imperial South 4/5 Garage [Member] | Tax Year 2 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     80.00%      
Port Imperial South 4/5 Garage [Member] | Tax Year 3 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     80.00%      
Port Imperial South 4/5 Garage [Member] | Tax Year 4 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     80.00%      
Port Imperial South 4/5 Garage [Member] | Tax Year 5 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     80.00%      
Port Imperial South 1/3 Garage [Member]            
Commitments And Contingencies [Line Items]            
Project period     5 years      
Percentage of taxes paid based on the land value     100.00%      
Port Imperial South 1/3 Garage [Member] | Tax Year 1 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     0.00%      
Port Imperial South 1/3 Garage [Member] | Tax Year 2 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     95.00%      
Port Imperial South 1/3 Garage [Member] | Tax Year 3 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     95.00%      
Port Imperial South 1/3 Garage [Member] | Tax Year 4 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     95.00%      
Port Imperial South 1/3 Garage [Member] | Tax Year 5 [Member]            
Commitments And Contingencies [Line Items]            
Annual percentage of cost for phase in     95.00%      
Port Imperial Hotel Development [Member]            
Commitments And Contingencies [Line Items]            
Project period     15 years      
Percentage of PILOT on project costs     2.00%      
Port Imperial South 11 Development [Member]            
Commitments And Contingencies [Line Items]            
Project period     15 years      
Percentage of PILOT on gross revenues     10.00%      
111 River Realty [Member]            
Commitments And Contingencies [Line Items]            
Payments in lieu of property taxes (PILOT) 352,000 381,000 $ 1,100,000 995,000    
Annual Payments in lieu of property taxes (PILOT)         $ 1,227,708  
111 River Realty [Member] | Scenario, Forecast [Member]            
Commitments And Contingencies [Line Items]            
Annual Payments in lieu of property taxes (PILOT)           $ 1,406,064
Monaco [Member]            
Commitments And Contingencies [Line Items]            
Project period     10 years      
Payments in lieu of property taxes (PILOT) $ 635,000 $ 558,000 $ 1,865,000 $ 1,106,000    
Percentage of PILOT on gross revenues     10.00%      
Marbella Tower Urban Renewal Associates LLC [Member]            
Commitments And Contingencies [Line Items]            
Percentage of PILOT on project costs     15.00%      
Payments in lieu of property taxes (PILOT)     $ 378,000      
Port Imperial South Parcel 8/9 [Member]            
Commitments And Contingencies [Line Items]            
Project period     25 years      
Port Imperial South Parcel 8/9 [Member] | Years 1-10 [Member]            
Commitments And Contingencies [Line Items]            
Percentage of PILOT on project costs     11.00%      
Port Imperial South Parcel 8/9 [Member] | Years 11-18 [Member]            
Commitments And Contingencies [Line Items]            
Percentage of PILOT on gross revenues     12.50%      
Port Imperial South Parcel 8/9 [Member] | Years 19-25 [Member]            
Commitments And Contingencies [Line Items]            
Percentage of PILOT on gross revenues     14.00%